A fatal train derailment in the southern state of Oaxaca has claimed the lives of at least 13 people, an incident likely to revive opposition criticisms regarding the speed and execution of the country's key government projects.
The crash occurred on the trans-isthmus railway, a route constructed to connect the Atlantic Ocean and Pacific Ocean across the thinnest stretch of the Isthmus of Tehuantepec. This endeavor was intended to provide an competing rail corridor to the Panama Canal, intended to promote commercial progress in the area.
“We shall rigorously clarify what caused this incident,” affirmed the head of state.
The leader confirmed that, of the approximately 250 individuals on board, another 98 were injured, with five of those in serious condition. The leader noted plans to visit Oaxaca to confer with those involved.
Major Initiative of Former Government
The Interoceanic Train was a cornerstone development scheme of the former leader, whose term finished the year before. This project was a hallmark of his government's strategic goals for the southern region.
Another multi-billion dollar railway undertaking from that era, a passenger and freight circuit around the Yucatán Peninsula, was also part of the wider plan to kickstart the economic fortunes of a historically less developed part of the country.
Construction Oversight and Safety Concerns
The development of both rail lines was managed by the army, marking a dramatic growth of its responsibilities in civilian projects. They were built at an fast-tracked pace, beating expectations to be at least partly launched before the end of that administration.
However, this rushed timetable had also raised significant concerns over safety standards.
- Sunday's crash was the third event on the Interoceanic Train in the current year.
- This encompasses an previous collision this month when a train hit a truck at a level crossing.
- The other major rail project has also had several non-deadly derailments.
Calls for Review and Suspension
In the wake of the disaster, the head of a key rival party urged an immediate suspension in the building and running of all comparable projects.
This stoppage was requested pending a comprehensive safety audit. The party stated that the situation "requires prompt explanations."
In response, the head of state asserted that the train had been operating in complete accordance with all security protocols. Commitments were given that the government would remain "accountable" in both the development and operation of these national projects.